William Bellamy Junior School

Client
London Borough of Barking and Dagenham
Sector
Education
Services
Site Solutions
Duration
May 2012-September 2012

Full Project Details

Our role: We were approached in May to design and construct a single-storey classroom with essential facilities in record time, ready for the new intake of students in September.

One of the first schools in the Dagenham region opened in 1877, and during the 1960s numbers throughout the area began to swell. In response, a new purpose-built open school plan was designed and opened in 1970. Now called William Bellamy Junior, the school has experienced growth ever since.

Achieving value for money together

In response to the school's rapid increase in students, we instilled a close, collaborative, open approach and worked alongside the school to ensure best value for money within their strict budget constraints.

Despite a limited budget, we were able to provide a single-storey, high quality solution with a sink and wet area, plastisol external envelope, air conditioning (heating and cooling), UPVC windows and doors, vinyl faced plasterboard walls and ceilings, and heavy duty carpet tiles. We also formed a connection to the existing school by constructing a hallway to link the two together.

Delivering with speed

Our in-house experts were at the ready, and despite a standing start, offered an impressive turnaround to meet the critical deadline. In just 17 weeks from the initial enquiry, with only six weeks spent on site, we made sure the class was fully operational and ready to house a class full of warm, happy children.

The engineering behind our swift delivery

Our innovative approach to offsite manufacturing and preassembly (DfMA) is making waves in the construction industry. Our in-house facilities have helped us perfect the construction process, offering full control over quality, safety, CO2 emissions and programme certainty.

Having these facilities in-house means we can offer our clients a unique advantage – no time wasted with external providers. Our factory is dedicated to serving Laing O'Rourke projects, and is run by a team of DfMA specialists ready to hit the ground running to achieve the strictest of programmes.

  • Rapid response time – a 17 week turnaround
  • Minimal presence on site – six weeks only
  • Maximised value within a strict budget